S.No. | Tower Name | Status |
---|---|---|
1 | Tower-A | Terrace Slab Completed |
2 | Tower-B | Terrace Slab Completed |
3 | Tower-C | Terrace Slab Completed |
4 | Tower-D | Terrace Slab Completed |
5 | Club | Terrace Slab Completed |
6 | Podium | Podium Slab Completed |
Basement Status : Plastering and Ceiling Painting work in advanced stage of progress. Snagging/De-snagging process initiated for Handing over to Facility Management Team.
Club : Finishing & Interiors work in progress (99% works completed).
Tower-A | |
---|---|
Fire Fighting | 2nd to 39th Floor Completed (Header & Branch Piping) |
Plumbing | 2nd to 39th Floor Completed (Concealed Fittings & Piping) |
Ips Work | 2nd to 39th Floor Completed |
Gypsum Plaster/Pop | 2nd to 39th Floor Completed |
Waterproofing | 2nd to 39th Floor Completed |
Stone Work (Living/Dining) | 2nd to 39th Floor Installed |
Balcony Railing | Completed (100%). |
UPVC windows | Completed (100%) |
Tower-B | |
---|---|
Fire Fighting | 2nd to 39th Floor Completed (Header & Branch Piping) |
Plumbing | 2nd to 39th Floor Completed (Concealed Fittings & Piping) |
Ips Work | 2nd to 39th Floor Completed |
Gypsum Plaster/Pop | 2nd to 39th Floor Completed |
Waterproofing | 2nd to 39th Floor Completed |
Stone Work (Living/Dining) | 2nd to 39th Floor Installed |
Balcony Railing | Completed (100%) |
UPVC windows | Completed (100%) |
Tower-C | |
---|---|
Fire Fighting | 2nd to 39th Floor Completed(Header & Branch Piping) |
Plumbing | 2nd to 39th Floor Completed(Concealed Fittings & Piping) |
Ips Work | 2nd to 39th Floor Completed |
Gypsum Plaster/Pop | 2nd to 39th Floor Completed |
Waterproofing | 2nd to 39th Floor Completed |
Stone Work (Living/Dining) | 2nd to 39th Floor Installed |
Balcony Railing | Completed (100%). |
UPVC windows | Completed (100%) |
Tower-D | |
---|---|
Fire Fighting | 2nd to 39th Floor Completed (Header & Branch Piping) |
Plumbing | 2nd to 39th Floor Completed (Concealed Fittings & Piping) |
Ips Work | 2nd to 39th Floor Completed |
Gypsum Plaster/Pop | 2nd to 39th Floor Completed |
Waterproofing | 2nd to 39th Floor Completed |
Stone Work (Living/Dining) | 2nd to 39th Floor Installed |
Balcony Railing | Work commenced, baluster, top rail completed, glass fixing started (98%). |
UPVC windows | Work in progress (100%) |